Greetings FL-IX Members,
The maintenance that was previously scheduled for Wednesday, December 4th at DataBank has been postponed until early January 2025 as some of the cabling needed to complete the task has been backordered until later this month. Once the remaining cables arrive, we will then schedule a new date for this maintenance.
If you have any questions, please feel free to contact me directly.
Regards,
Randy Epstein
Executive Director
Email: [email protected]
Mobile: +1 561-756-4475
Office: +1 888-925-4678
Fax: +1 561-431-0437
P Please consider the environment before printing this e-mail
From: Randy Epstein <[email protected]>
Date: Monday, November 18, 2024 at 4:30 PM
To: "[email protected]" <[email protected]>
Subject: FL-IX switch replacement at DataBank - Wednesday, December 4th at 12:01am
Greetings FL-IX Members,
On Wednesday, December 4th, at 12:01am Eastern Time, we will be replacing the edge switch members connect to at DataBank (36 NE 2nd St, Suite 700, Miami) with a higher capacity switch, as well as replacing the existing patch cables.
Estimated downtime for members at this location will be up to three (3) hours, however, our maintenance window will be from 12:01am to 5am Eastern time. We will of course try to minimize downtime as best we can.
For the duration of the maintenance, we will block BGP traffic only to those members affected by the maintenance as described in BCP 214. Sessions will re-establish after the maintenance has concluded. No action is required on your part. To those members not directly connected to this switch, you will see sessions go down to the members that are directly connected, so please keep that in mind.
Regards,
Randy Epstein
Executive Director
Email: [email protected]
Mobile: +1 561-756-4475
Office: +1 888-925-4678
Fax: +1 561-431-0437
P Please consider the environment before printing this e-mail